Karachi

PV | Diesel | Grid

Client
Shell
Karatchi - new efficiency-technics
at the gate to central asia
Pakistan
Left
As the local public electricity grid is often subject to power outages, the client opted for DHYBRID’s UPP technology to ensure 100% grid stability. The annual reduction in energy requirements for this DHYBRID System in Karachi is predicted to be around 182,000 kWh, which corresponds to approximately 53,000 liters of diesel fuel. The DHYBRID UPP Systemcontroll automatically operates in diesel and grid modes.

System Type

PV | Diesel | Grid

Installation Type

UPP control system

Sunshine Hours Karachi

2,950 hours / year

SIZE

Size of Plant Diesel

520

kVA

Size of Plant PV

102

kWp

SAVINGS

Savings Energy

182,000

kWh / year

Savings CO2

127,400

kg / year

40,4

tons of waste recycled

Subscribe the DHYBRID-Newsletter

Do you want to be notified about new products, shows and specials?
Get the latest news and infos and join our email newsletter.

E-Mail *
First Name
Last Name
Gender   male       female
close