INDUSTRY / UTILITY
Sri Lanka
Colombo
PV | BESS | Diesel
Client
Lanka Electricity Company
Sri Lanka's first ever grid-tied Microgrid
System Type
PV | BESS | Diesel
Installation Type
Universal Power Platform
Sunshine Hours Colombo
2,700 hours / year
SIZE
Size of Plant Diesel
350
kVA
Size of Battery System
400 / 400
kW / kWh
Size of Plant PV
350
kWp
SAVINGS
Savings Diesel
141,750
liter / year
Savings Energy
525,000
kWh / year
Savings CO2
367,500
kg / year
50
homes' energy use for one year
923,525
miles driven by an average passenger vehicle
129
tons of waste recycled